Markup and margin both describe profit, but they measure it against different numbers. Mixing them up is one of the most common pricing mistakes in construction, and it always goes the same way: you keep less than you planned.
The two formulas
- Markup = profit / cost
- Margin = profit / price
On a job that costs $10,000 and sells for $12,500, the profit is $2,500. That's a 25% markup ($2,500 / $10,000) but only a 20% margin ($2,500 / $12,500).
To go from the margin you want to the markup you need: markup = margin / (1 - margin). To go the other way: margin = markup / (1 + markup).
Conversion table
| Margin you want to keep | Markup you need on cost |
|---|---|
| 10% | 11.1% |
| 15% | 17.6% |
| 20% | 25.0% |
| 25% | 33.3% |
| 30% | 42.9% |
| 35% | 53.8% |
| 40% | 66.7% |
| 50% | 100.0% |
And the mistake in reverse, the margin you actually keep when you mark up by:
| Markup on cost | Margin you keep |
|---|---|
| 10% | 9.1% |
| 15% | 13.0% |
| 20% | 16.7% |
| 25% | 20.0% |
| 30% | 23.1% |
| 50% | 33.3% |
| 100% | 50.0% |
Why it matters on a real job
Say your overhead and profit target is a 20% margin, and you price a $50,000 job by adding 20% to cost. Price: $60,000. Profit: $10,000. Margin: $10,000 / $60,000 = 16.7%, not 20%.
To actually keep 20%, divide cost by 0.80: $50,000 / 0.80 = $62,500. That's a 25% markup, and $2,500 more on one job.
Is your pricing leaking money? Free 60-second check, five questions. Answers stay in your browser.
Which one should contractors use?
Price with margin, because it's how your profit and loss statement reads: profit as a share of revenue. If your business needs 20% of every dollar of sales to cover overhead and profit, price every job to a 20% margin by dividing its cost by 0.80.
Use markup only as the number you apply on a spreadsheet, and convert it from your target margin with the table above. The markup vs margin calculator does the conversion, and the contractor markup calculator prices a whole job from materials, labor and overhead.
Where overhead fits
Overhead is a cost, not profit. Add your overhead to the job's cost first, then price to the margin you want to keep as profit. If you fold overhead into the "markup", make sure the markup is big enough to cover both. The guide to calculating business overhead shows how to find your overhead percentage.
FAQ
What's the difference between markup and margin in construction? Markup is profit divided by cost; margin is profit divided by the selling price. A 25% markup is a 20% margin.
What markup do I need for a 30% margin? 42.9%. Divide your cost by 0.70 to get the price.
Is a 20% markup the same as a 20% margin? No. A 20% markup leaves a 16.7% margin. To keep 20%, you need a 25% markup.
What margin should a contractor aim for? There's no single right number. Work out what your business needs to keep after overhead for profit, slow months and equipment, and price every job to at least that margin.
Run your numbers: the free markup vs margin calculator converts any margin to the markup you need. No sign-up.